SUBSECRETARIA DE INFRAESTRUCTURA |
DIRECCION
GENERAL DE CONSERVACION DE CARRETERAS |
Programa
Nacional de Conservación de Carreteras |
Avance Físico
- Financiero |
|
|
|
|
|
|
|
MAYO
2024 |
No. |
NOMBRE DE LA OBRA |
UBICACIÓN |
META |
ASIGNACIÓN |
AVANCE FÍSICO |
AVANCE FINANCIERO
% |
KM INICIAL |
KM FINAL |
UNIDAD |
% |
|
MORELOS |
|
|
|
13,350,853.00 |
|
|
99.99 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Conservación Periódica de Tramos |
|
|
0.00 |
2,042,132.16 |
|
|
100.00 |
|
|
|
|
|
|
|
|
|
|
Bacheo y Microcarpeta |
|
|
0.00 |
1,395,846.28 |
|
|
100.00 |
|
Michapa - Puente de Ixtla |
0.00 |
5.00 |
finiquito |
172,750.75 |
|
|
100.00 |
|
Alpuyeca - Grutas de Cacahuamilpa (Cpo. B) |
33.00 |
36.00 |
finiquito |
104,145.42 |
|
|
100.00 |
|
Lim. de Edos. DF /Mex.-Oaxtepec |
60.00 |
72.60 |
finiquito |
1,011,804.69 |
|
|
100.00 |
|
Ramal a Lagunas de Zempoala |
0.00 |
3.00 |
finiquito |
107,145.42 |
|
|
100.00 |
|
|
|
|
|
|
|
|
|
|
Bacheo y Sello |
|
|
0.00 |
646,285.88 |
|
|
100.00 |
|
Cuautla - Lim. de Edos. Mor./Pue. |
99.00 |
103.00 |
finiquito |
298,433.98 |
|
|
100.00 |
|
Lim. de Edos. Mex./Mor.-Cuautla (Cpo. A) |
53.00 |
56.00 |
finiquito |
223,825.48 |
|
|
100.00 |
|
Alpuyeca - Grutas de Cacahuamilpa (Cpo. B) |
17.00 |
23.00 |
finiquito |
124,026.42 |
|
|
100.00 |
|
|
|
|
|
|
|
|
|
|
Atención a Puntos de Conflicto |
|
|
0.00 |
4,056,214.26 |
|
|
100.00 |
|
Tlalpan - Lim. Edos. CDMX/Mor * |
21+000 |
28+000 |
finiquito |
4,056,214.26 |
|
|
100.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Conservación Rutinaria de Tramos |
|
|
0.00 |
4,317,362.16 |
|
|
99.96 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Señalamiento Horizontal |
|
|
0.00 |
1,637,042.76 |
|
|
100.00 |
|
|
|
|
|
|
|
|
|
|
Conservación Rutinaria de Puentes |
|
|
0.00 |
749,990.87 |
|
|
100.00 |
|
|
|
|
|
|
|
|
|
|
Otros Subprogramas |
|
|
|
548,110.79 |
|
|
100.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|