SUBSECRETARIA DE INFRAESTRUCTURA |
DIRECCION
GENERAL DE CONSERVACION DE CARRETERAS |
Programa
Nacional de Conservación de Carreteras |
Avance Físico
- Financiero |
|
|
|
|
|
|
|
MAYO
2024 |
No. |
NOMBRE DE LA OBRA |
UBICACIÓN |
META |
ASIGNACIÓN |
AVANCE FÍSICO |
AVANCE FINANCIERO
% |
KM INICIAL |
KM FINAL |
UNIDAD |
% |
|
SINALOA |
|
|
|
55,767,448.64 |
|
|
94.07 |
|
|
|
|
|
|
|
|
|
|
RECONSTRUCCIÓN |
|
|
|
38,788,479.14 |
|
|
100.00 |
|
|
|
|
|
|
|
|
|
|
Conservación Periódica de Tramos |
|
|
0.00 |
38,788,479.14 |
|
|
100.00 |
|
|
|
|
|
|
|
|
|
|
Fresado y Carpeta |
|
|
0.00 |
22,385,556.74 |
|
|
100.00 |
|
Guasave - Los Mochis (Cpo. A) |
146.00 |
149.00 |
finiquito |
64,239.65 |
|
|
100.00 |
|
Guasave - Los Mochis (Cpo. A) |
178.30 |
181.05 |
finiquito |
1,451,025.14 |
|
|
100.00 |
|
Guasave - Los Mochis (Cpo. B) |
146.00 |
150.00 |
finiquito |
585,234.41 |
|
|
100.00 |
|
Los Mochis - Lim. Edos. Sin./Son. (Cpo. A) |
43.82 |
51.63 |
finiquito |
11,801,509.92 |
|
|
100.00 |
|
Los Mochis - Lim. Edos. Sin./Son. (Cpo. B) |
6.50 |
12.94 |
finiquito |
5,476,530.21 |
|
|
100.00 |
|
Los Mochis - Lim. Edos. Sin./Son. (Cpo. B) |
15.03 |
19.45 |
finiquito |
3,007,017.41 |
|
|
100.00 |
|
|
|
|
|
|
|
|
|
|
Recuperación de Pavimentos y Carpeta |
|
|
0.00 |
9,563,712.21 |
|
|
100.00 |
|
Km 3+000 - Ent. Costa Rica |
119.00 |
124.00 |
finiquito |
9,563,712.21 |
|
|
100.00 |
|
|
|
|
|
|
|
|
|
|
Bacheo y Microcarpeta |
|
|
0.00 |
6,839,210.19 |
|
|
100.00 |
|
Km 3+000 - Ent. Costa Rica (2 Cpos.) |
202.90 |
207.40 |
finiquito |
6,839,210.19 |
|
|
100.00 |
|
Saldo |
|
|
|
0.00 |
|
|
0.00 |
|
|
|
|
|
|
|
|
|
|
Conservación Periódica de Puentes |
|
|
0.00 |
459,414.91 |
|
|
100.00 |
|
|
|
|
|
|
|
|
|
|
Conservación Rutinaria de Tramos |
|
|
0.00 |
11,964,086.50 |
|
|
88.50 |
|
|
|
|
|
|
|
|
|
|
Señalamiento Horizontal |
|
|
0.00 |
1,687,182.00 |
|
|
100.00 |
|
|
|
|
|
|
|
|
|
|
Conservación Rutinaria de Puentes |
|
|
0.00 |
934,560.65 |
|
|
100.00 |
|
|
|
|
|
|
|
|
|
|
Otros Subprogramas |
|
|
|
1,933,725.44 |
|
|
0.09 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
( ** ) Conservación Rutinaria de Tramos en el
contrato 2023-25-CB-A-002-W-00-2023, se realizó la terminación anticipada de
la obra, reduciendose los montos por un importe de $2,134,836.07 pesos. |
|
( *** ) Señalamiento Horizontal, Se redujo la
asignación modificada de $20,218,000.00 a $12,304,078.41. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|