SUBSECRETARIA DE INFRAESTRUCTURA |
DIRECCION
GENERAL DE CONSERVACION DE CARRETERAS |
Programa
Nacional de Conservación de Carreteras |
Avance Físico
- Financiero |
|
|
|
|
|
|
|
MAYO
2024 |
No. |
NOMBRE DE LA OBRA |
UBICACIÓN |
META |
ASIGNACIÓN |
AVANCE FÍSICO |
AVANCE FINANCIERO
% |
KM INICIAL |
KM FINAL |
UNIDAD |
% |
|
VERACRUZ |
|
|
|
226,602,696.64 |
|
|
95.39 |
|
|
|
|
|
|
|
|
|
|
RECONSTRUCCIÓN |
|
|
|
13,665,633.77 |
|
|
95.00 |
|
|
|
|
|
|
|
|
|
|
Reconstrucción de Puentes |
|
|
0.00 |
13,665,633.77 |
|
|
95.00 |
|
Boca del Rio I |
116+700 |
116+700 |
finiquito |
7,174,716.09 |
|
|
90.47 |
|
Tezechoacan |
57+100 |
57+100 |
finiquito |
6,490,917.68 |
|
|
100.00 |
|
|
|
|
|
|
|
|
|
|
Conservación Periódica de Tramos |
|
|
0.00 |
138,375,104.18 |
|
|
97.66 |
|
|
|
|
|
|
|
|
|
|
Fresado y Carpeta |
|
|
0.00 |
13,646,913.41 |
|
|
100.00 |
|
Lim. Edos. Pue./ Ver.- Perote T.A. (2) |
32+000 |
35+100 |
finiquito |
7,605,572.43 |
|
|
100.00 |
|
Acayucan - Lim. Edos. Ver./Oax. (Cpos. A y B) (3) |
69+300 |
71+400 |
finiquito |
6,041,340.98 |
|
|
100.00 |
|
|
|
|
|
|
|
|
|
|
Recuperación de Pavimento y Carpeta |
|
|
0.00 |
3,625,942.08 |
|
|
100.00 |
|
Lim. Edos. Hgo./Ver. - Tempoal |
239.60 |
241.00 |
finiquito |
3,625,942.08 |
|
|
100.00 |
|
|
|
|
|
|
|
|
|
|
Bacheo y Carpeta |
|
|
0.00 |
37,975,301.32 |
|
|
100.00 |
|
Fortin de las Flores - T Conejos |
79+000 |
82+000 |
finiquito |
7,605,572.43 |
|
|
100.00 |
|
Cordoba - Paso del Toro T.A. |
7+500 |
14+500 |
finiquito |
7,579,292.02 |
|
|
100.00 |
|
Libramiento de Veracruz (Cpo. B) T.A. |
8+900 |
12+200 |
finiquito |
7,605,572.43 |
|
|
100.00 |
|
Libramiento de Veracruz (Cpo. A) T.A. |
8+900 |
12+200 |
finiquito |
7,605,572.43 |
|
|
100.00 |
|
Acayucan - Lim. Edos. Ver./Oax. |
84+000 |
87+400 |
finiquito |
7,579,292.02 |
|
|
100.00 |
|
|
|
|
|
|
|
|
|
|
Bacheo y Microcarpeta |
|
|
0.00 |
49,850,116.12 |
|
|
100.00 |
|
Tuxpan - Tampico (Cpo. B) |
147+000 |
149+300 |
finiquito |
3,625,942.08 |
|
|
100.00 |
|
Fortin de las Flores - T Conejos |
34+000 |
38+000 |
finiquito |
7,605,572.43 |
|
|
100.00 |
|
Coatzacoalcos - Acayucan (Cpo. B) |
6+000 |
18+800 |
finiquito |
11,730,008.79 |
|
|
100.00 |
|
Coatzacoalcos - Acayucan (Cpo. A) |
6+000 |
17+300 |
finiquito |
11,730,008.79 |
|
|
100.00 |
|
Coatzacoalcos - Acayucan |
32+000 |
34+000 |
finiquito |
7,579,292.02 |
|
|
100.00 |
|
Coatzacoalcos - Acayucan |
38+700 |
41+700 |
finiquito |
7,579,292.02 |
|
|
100.00 |
|
|
|
|
|
|
|
|
|
|
Microaglomerado |
|
|
0.00 |
33,276,831.26 |
|
|
90.28 |
|
Xalapa - Tamarindo (Cpo. B) |
15+000 |
21+400 |
finiquito |
7,605,572.43 |
|
|
100.00 |
|
Lim. Edos. S.L.P./Ver.- Tampico |
83+570 |
94+000 |
finiquito |
3,625,942.08 |
|
|
100.00 |
|
Lim. Edos. Pue./Ver.- Tihuatlan |
211+500 |
215+500 |
finiquito |
3,625,942.08 |
|
|
100.00 |
|
Fortin de las Flores - T Conejos |
1+630 |
13+000 |
finiquito |
7,605,572.43 |
|
|
100.00 |
|
La Tinaja - Cd. Aleman T.A. |
10+000 |
21+700 |
finiquito |
7,579,292.02 |
|
|
100.00 |
|
SALDO |
|
|
|
3,234,510.24 |
|
|
0.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Programa de prevención de Riego de Protección |
|
|
59.68 |
2,058,379.63 |
|
|
100.00 |
|
|
|
|
|
|
|
|
|
|
Conservación Periódica de Puentes |
|
|
0.00 |
3,950,848.76 |
|
|
99.99 |
|
|
|
|
|
|
|
|
|
|
Atención a Puntos de Conflicto |
|
|
0.00 |
11,734,302.04 |
|
|
54.35 |
|
(Rampa de Frenado) Santa Cruz - Tlapacoyan (18) |
0+000 |
1+350 |
finiquito |
3,552,365.70 |
|
|
100.00 |
|
(Correccion de Curva) Nautla - Cardel del Km. 178+000 al 180+000 |
178+000 |
180+000 |
finiquito |
2,825,126.73 |
|
|
100.00 |
|
SALDO |
|
|
|
5,356,809.61 |
|
|
0.00 |
|
|
|
|
|
|
|
|
|
|
Conservación Rutinaria de Tramos |
|
|
0.00 |
43,389,727.28 |
|
|
98.00 |
|
|
|
|
|
|
|
|
|
|
Señalamiento Horizontal |
|
|
0.00 |
9,095,379.84 |
|
|
96.61 |
|
|
|
|
|
|
|
|
|
|
Otros Subprogramas |
|
|
0.00 |
4,333,321.14 |
|
|
100.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|